Activities & preds. are the same as in the PowerPoint but the durations are different. You are required to draw an AON diagram f…

FIND A SOLUTION AT Academic Writers Bay

All the ES-EF lines I call horizontal and ES-LS or EF-LE lines vertical. When you determine the CP route, examine the figures in the horizontals and verticals. Do you notice the difference on the CP-route verticals from the non-CP verticals?
Activity predecessor Duration
a – 10 days
b -. 8
c a 6
d a 8
e a 12
f b,c 8
g d 10
h d,e 12
i f 12
j g,h 8